nblogo.jpg (24791 bytes)

                                                               

North Branch Construction, Inc.                    

Our Mission: To provide a level of value, quality and

                                                                                service that is unrivaled in the construction industry.   

[ Home ] [ Contents ] [ Contact Us-More information ]

 
[ Introduction ] [ Project Portfolio ] [ NB News Highlights ] [ Meet the Principals ] [ Employment Opportunities ]  [ Subcontractors Pre-qualification ] [ Upcoming Bids / Addendums ] [ Current Projects ] [ Sustainable Construction] [ Employees Only ]

Voted Best of Business in 2008  by readers of NH Business Review

ABCplaque.jpg (16116 bytes)

 Five Consecutive Years ABC Excellence in Construction Awards  Institutional Over $2 Million Category with three years President's "Best of the Best"


Department of Transportation, Division of Motor Vehicles Addition, Concord, NH

  • State of NH, Department of Transportation Project
  • $4.1 million Design/Build Contract
  • 34,000 square foot addition
  • 6 month construction schedule

North Branch was chosen Design/Build contractor as low bidder for the design and construction of the Division of Motor Vehicles Phase II (addition) for the Department of Safety, State of New Hampshire, Department of Transportation. The facility is located on Hazen Drive in Concord, NH. North Branch was awarded the contract in March and with design development complete, sitework began in early April.

Foundations were completed in May and erection of the structural steel began in early June. By mid July roof trusses were being hoisted into place. By early September the roof construction was complete and exterior finishes (brick veneer and EIFS) were being installed and interior drywall underway. The project was completed in December 2004, 2 weeks ahead of contract schedule. In early January, the State of New Hampshire, Department of Transportation, Division of Motor Vehicles, dedicated the building to the former governor, Steven Merrill.

Udelsman Associates of Hollis, NH teamed with North Branch Construction for the design of the 34,000 square foot, two story $4.1 million project. Aerial photo provided by Tom Hettinger.

[ Henniker Fire/Rescue ] [ Hillsboro Police ] [ State of NH DOT - John O. Morton Building ] [ Somerville Street Fire Station, Engine No. 7 ] [ NH Fire Safety ] [ Municipal ] [ Sunapee Safety Complex ]


North Branch Construction, Inc.      

76 Old Turnpike Road, Concord, NH 03301  (603) 224-3233 - FAX (603) 225-7165.

email:info@northbranch.net

 North Branch Construction is a member of the U.S. Green Building Council, Associated Builders and Contractors, Inc.(NH/VT Chapter), American Institute of Architects, Plan NH, the NH Preservation Alliance and Granite State Chapter of the National Association of Women in Construction

 

 

 

 

Hit Counter